Hydro-Québec cautions it can’t meet surging demand over next decade
Posted November 3, 2026 7:01 am.
Hydro-Québec is not counting on nuclear power to meet the strong growth in demand projected over the next 15 years. The state-owned utility is, however, keeping the door open for the longer term.
Although Prime Minister Mark Carney’s government wants to revive the nuclear industry in the country, Hydro-Québec will not be the first to step forward, says its executive vice president in charge of energy strategy, Dave Rhéaume, in an interview on the sidelines of the unveiling of the 2027–2041 supply plan.
The state-owned utility anticipates an “extremely high” increase in energy demand. Thanks to its hydroelectric grid and energy efficiency goals, Quebec has the luxury of taking the time to observe what other provinces are doing, Rhéaume believes.
“We don’t need to be the first to stumble with a new technology,” he replied. “We should use the advantage we have to learn from others.”
No power plant has been built in Canada since the early 1990s. The deployment of next-generation nuclear projects is still in its early stages.
“We’ll see how much it cost,” said Rhéaume. “We’ll see how it works. So, it will be a point of interest.”
There is a growing enthusiasm for nuclear energy around the world, driven by the development of artificial intelligence, the electrification of transportation, and the decarbonization of the economy.
This enthusiasm is also evident in Canada. The Montreal-based company AtkinsRéalis, formerly SNC-Lavalin, has repeatedly cited strong demand for nuclear power over the past few quarters.
For its part, Ottawa announced in June its intention to build up to ten new nuclear reactors over the next fifteen years.
Currently, Canada has four nuclear power plants—three in Ontario and one in New Brunswick—which generate about 15 per cent of the country’s electricity.
Hydro-Québec long had only one plant in its generation portfolio, Gentilly-2, but it closed in 2012.
Nuclear energy produces very few carbon emissions compared to fossil fuels. However, the management of radioactive waste poses other environmental challenges. Fears of an accident—even though the industry insists that the technology is safe—also make it difficult to gain public acceptance.
Rhéaume believes that Hydro-Québec must adopt an open stance toward the industry.
Despite the substantial investments planned through 2041, Hydro-Québec will not yet have “ensured the full decarbonization of everything that needs to be done,” he points out. “We must continue to monitor developments in all energy sectors to see how we can continue to serve Quebec.”
An energy shortfall in 2029
Hydro-Québec forecasts that it will be necessary to find new sources of supply to meet Quebec’s demand as early as 2029, according to the 2027–2041 supply plan.
As it develops additional generation capacity, the state-owned utility will experience periods of slight energy shortfalls between now and 2041, according to the scenario outlined in the document. These shortfalls could be offset by importing electricity from neighbouring provinces or the United States.
“We need new generation assets to come online, because if we’re not able to build new generation capacity, demand will rise and production won’t keep up. And that’s when we’ll run into a problem,” summarizes Rhéaume.
He notes that this scenario is based on “normal” conditions. The exceptionally dry weather of the past three years is already forcing Hydro-Québec to manage its reservoirs cautiously.
The polar vortex last January and February, for example, forced Hydro-Québec to implement power outages. Its most recent financial results are also under pressure, as it has fewer opportunities to export electricity.
To meet demand, the state-owned utility plans to add 24,000 megawatts of generating capacity by 2041. It is also focusing on energy efficiency, aiming to achieve savings of 21 terawatt-hours by 2035.
The supply plan, unveiled Tuesday, paints a picture of a Quebec with an ever-increasing appetite for electricity, which will need to make “unprecedented” investments to satisfy its customers’ demand.
Hydro-Québec anticipates that Quebec’s electricity demand will increase by 60 terawatt-hours by 2041, representing nearly one-third of current demand. The increase is primarily attributable to the electrification of transportation, industrial demand, and the decarbonization of buildings.
This trend had already been highlighted three years ago with the unveiling of the state-owned utility’s 2035 action plan.
The new supply plan presents a relatively similar scenario, but with a “more gradual” increase in demand, summarizes Rhéaume.
–This report by La Presse Canadienne was translated by CityNews